EXPERTISE / CARBON FIBRE

Carbon fibre strengthening in Tunisia: bridges, structures and buildings

BBTP strengthens concrete beams, slabs and decks by bonding Sika® CarboDur® S plates and carbon-fibre fabric: light, quick-to-install strengthening that restores capacity without adding weight.

HOW IT WORKS

How does carbon fibre strengthening work?

Carbon-fibre plates or fabric are bonded with epoxy resin to the tension faces of the concrete, usually the underside of beams and slabs. They work together with the existing reinforcement and take part of the load.

Carbon-fibre composites combine very high tensile strength, low weight and immunity to corrosion. The strengthening adds virtually no weight and does not reduce the clearance under the deck.

WHEN TO STRENGTHEN

When does a structure need strengthening?

The need is established by an assessment of the structure and a design calculation by an engineering office, which sets the amount and position of carbon to install.

  • Corroded reinforcement that has lost part of its section
  • Heavier loads or a change in use of the structure
  • Bending or shear cracks in the beams
  • A design or construction defect to correct
  • Upgrading to more recent codes

THE SOLUTIONS

Plates or fabric?

The two are often combined on the same structure, depending on the loads.

01

Sika® CarboDur® S plates

Rigid carbon-fibre strips bonded to the underside of beams and slabs. They strengthen members in bending.

02

Carbon-fibre fabric

Flexible fabric impregnated with resin on site. It follows the shape: shear strengthening of beams, confinement of columns and piers.

OUR METHOD

Strengthening in five steps.

  1. Assessment and design

    Survey of the structure and design of the strengthening by the engineering office.

  2. Substrate repair

    Treating damaged concrete and corroded reinforcement before any bonding.

  3. Surface preparation

    Grinding or blasting the concrete, removing dust, and checking flatness and surface strength.

  4. Bonding

    Applying the epoxy adhesive, placing the plates or fabric and rolling them firmly in place.

  5. Checks and protection

    Checking adhesion by sounding, then protecting the strengthening.

THE ADVANTAGES

Light, discreet strengthening.

Compared with reinforced-concrete jacketing or additional post-tensioning, carbon fibre is often the lightest solution. The choice depends on the structure, and BBTP carries out all three techniques.

  • Negligible self-weight.
  • A material immune to corrosion.
  • Quick installation with little equipment.
  • Just a few millimetres thick: clearance and appearance preserved.

ON SITE

Before and after strengthening.

All photos ↗
Before — The structure before strengthening
BeforeThe structure before strengthening
After — Carbon plates on the deck soffit
AfterCarbon plates on the deck soffit
Before — Damaged deck soffit
BeforeDamaged deck soffit
After — Completed and protected strengthening
AfterCompleted and protected strengthening

WHY BBTP

Why entrust your strengthening to BBTP?

01

A speciality

BBTP specialises in repairing bridges and strengthening structures, including installing Sika® CarboDur® S plates and carbon-fibre fabric.

02

Field experience

Work in all 24 Tunisian governorates, notably for the Ministry of Equipment.

03

Passed-on know-how

Crews trained by Mohamed Salah Biri, former head of SOMATRA’s structures department.

FAQ

Carbon fibre: your questions.

Do you also work on buildings?

Yes. Beyond bridges and structures, BBTP repairs and strengthens buildings: residential and public buildings, factories, cement plants and industrial sites, with the same techniques.

Does carbon fibre replace the steel reinforcement?

No, it complements it. Corroded steel is treated and the concrete repaired first; the carbon then provides the missing capacity.

Who designs the strengthening?

An engineering office, based on the assessment of the structure. Its design calculation sets the number, position and section of the plates or fabric.

Does the structure have to be closed during the work?

Not necessarily: bonding is done under the deck, from scaffolding or platforms. Traffic arrangements, especially while the adhesive cures, are agreed with the engineering office and the project owner.

Is carbon fibre strengthening durable?

Yes, if it is correctly installed and protected: carbon fibre is immune to corrosion. Like the rest of the structure, it is checked during periodic inspections.

Where do you work?

Throughout Tunisia. BBTP works in all 24 governorates, notably for the Ministry of Equipment.

A STRUCTURE TO STRENGTHEN?

Let’s talk about your structure.

Project owners, design offices, contractors: tell us about the structure and the defects observed, and we will get back to you.

Contact us