Work in progress

Repair and strengthening of the El Kantara Roman causeway bridge (Djerba)

For the Regional Directorate of Equipment of Medenine, BBTP is repairing and strengthening the bridge on regional road RR117, which links Zarzis to the island of Djerba along the El Kantara Roman causeway, between the Boughrara lagoon and the Mediterranean.

Project page ↗
Featured

Rehabilitation of two road bridges over the railway in Sousse

As part of the national bridge rehabilitation programme, BBTP upgraded two road bridges over the railway in Sidi Abdelhamid (Sousse) for the Regional Directorate of Equipment of Sousse, in close collaboration with SNCFT.

Project page ↗
Client
Regional Directorate of Equipment, Sousse
In collaboration with
SNCFT (Tunisian National Railways)
Technical assistance
CEP design office
Location
Sidi Abdelhamid, Sousse

Works carried out

  • Deck jacking on temporary trestles, to unload the supports and repair them safely.
  • Concrete repair: rebuilding of damaged bearing plinths, pier caps and piers.
  • Resurfacing of the wearing course with asphalt concrete.
  • Protective painting of the concrete faces.
  • Installation of BN4 barriers.

Essential work for the safety of road users and of the rail traffic beneath the structures.

Reference

Repair and jacking of the Bizerte lift bridge

For the Regional Directorate of Equipment of Bizerte, BBTP carried out repair and jacking works on one of the country’s most iconic structures, in a marine setting above the channel.

Project page ↗
Client
Regional Directorate of Equipment, Bizerte
Structure
Bizerte lift bridge
Works
Repair and jacking
Location
Bizerte

Works carried out

  • Deck jacking, with safety packing on stacked steel plates.
  • Repair of the damaged bearing areas under the deck.
  • Works carried out from scaffolding fixed to the piers, above the water.
  • On-site monitoring of the jacking, under the deck.

Work in a marine setting, on a structure in use in the heart of the city.

Reference

Repair of a bridge over the Medjerda river in Slouguia (Béja)

For the Regional Directorate of Equipment of Béja, BBTP repaired this road bridge over the Medjerda river: deck jacking, construction of plinths and installation of bearings, treatment of damaged concrete, beam repair and carbon fibre strengthening.

Project page ↗
Client
Regional Directorate of Equipment, Béja
Structure
Bridge over the Medjerda river
Works
Repair, jacking and bearing installation
Location
Slouguia, Béja governorate

Works carried out

  • Deck jacking to free and treat the bearing areas.
  • The bridge was originally locked, with no bearings: plinths were built and bearings installed under the jacked deck, which has regained its freedom of movement.
  • Removal of damaged concrete and treatment of corroded reinforcement.
  • Repair and resurfacing of the deck beams.
  • Beam strengthening with carbon fibre laminates and fabrics.

Targeted repairs to extend the life of a Medjerda crossing.

Reference

Replacement of a pedestrian footbridge at Sousse railway station

BBTP replaced the old, cracked and deteriorated pedestrian footbridge at Sousse railway station with a new single-span structure of three precast girders on micropile foundations.

Project page ↗
Structure
Pedestrian footbridge, 1 span, 3 girders
Works
Demolition and rebuilding
Location
Sousse railway station, city centre
Acceptance
Partial acceptance granted without reservations

Works carried out

  • Removal and demolition of the old, cracked and deteriorated footbridge.
  • Deep foundations on micropiles, then reinforced-concrete piers and columns.
  • On-site precasting of the three reinforced-concrete girders by BBTP, lifting and placing with a mobile crane, then casting of the deck slab and access stairs.
  • Placing of the edge cornices with a telescopic handler.
  • Equipment and finishes: guardrails, anti-fall mesh, finishing screed and solar street lights.

A new structure replacing a cracked, deteriorated footbridge over the tracks at Sousse station.

Reference

Repair of a bridge over the Khmeyssia wadi in Zaghouan (RL636)

On this three-span girder bridge, BBTP replaced the carriageway and footway joints, strengthened the scoured foundations and rebuilt the approach embankments.

Project page ↗
Structure
Girder bridge, 3 spans, 2 abutments and 2 piers
Road
Local road RL636, chainage 4+400
Location
Khmeyssia wadi, Zaghouan governorate
Acceptance
Partial acceptance on 8 December 2020, without reservations

Works carried out

  • Replacement of the carriageway and footway expansion joints.
  • Reinforced-concrete jacketing of the scoured footings and filling of the voids under the abutment caps by injecting self-compacting concrete (SCC).
  • Construction of a retaining wall and rebuilding of the slope.

A complete restoration, from the deck equipment down to the foundations.

Before / after

Rehabilitation of a masonry arch bridge in Bir Bouregba (Nabeul)

Restoration of the structure and its surroundings, with gabion and stone-pitching bank protection.

Project page ↗
Before — The bridge overgrown with vegetation
BeforeThe bridge overgrown with vegetation
After — Rehabilitated bridge and landscaped surroundings
AfterRehabilitated bridge and landscaped surroundings
Before — Masonry and arches before works
BeforeMasonry and arches before works
After — Banks protected with gabions and stone pitching
AfterBanks protected with gabions and stone pitching
01

Expansion joint replacement

Removal of worn joints, rebuilding of anchorage zones and installation of new joints.

The technique ↗
02

Bearing replacement and deck jacking

Jacking under traffic, on jacking blocks or temporary trestles.

The technique ↗
03

Repair, surface treatment and maintenance

Work at height and in marine settings, by day and by night.

The technique ↗
04

Vehicle restraint systems

Guardrails, BN4 and DBA barriers.

The technique ↗
05

Additional post-tensioning

New anchorage blocks and deviators for the external post-tensioning.

The technique ↗
06

Concrete jacketing and crack injection

Strengthening of vertical or horizontal structural members.

The technique ↗
07

Carbon fibre strengthening

Carbon-fibre fabric and Sika® CarboDur® S plates.

The technique ↗
Before — The structure before strengthening
BeforeThe structure before strengthening
After — Carbon plates on the deck soffit
AfterCarbon plates on the deck soffit
Before — Damaged deck soffit
BeforeDamaged deck soffit
After — Completed and protected strengthening
AfterCompleted and protected strengthening