AFRICA / BRIDGES

Flood-damaged bridge or scour: assessment and repair

During a flood, the current digs out the ground around a bridge’s foundations: this is scour. The approach embankments erode and the footings are left exposed. BBTP, a Tunisian bridge specialist since 2002, has strengthened scoured foundations and studies requests from all over Africa.

WARNING SIGNS

Warning signs

After a flood, these signs mean the bridge should be inspected by a specialist:

  • Ground dug out around piers or abutments
  • Exposed foundation footings
  • Eroded approach embankments
  • Cracks in, or movement of, a pier or abutment
  • Debris piled up against the piers

If the bridge looks damaged, follow the authorities’ instructions and have it inspected by a professional; reopening it to traffic is for the authorities to decide.

WHAT WE DO

The techniques we use.

On the Khmeyssia wadi bridge, we strengthened the scoured foundations, jacketed the footings in reinforced concrete and rebuilt the approach embankments.

All our techniques ↗
01

Reinforced-concrete jacketing

A new reinforced-concrete shell around columns, beams or walls, and crack injection.

Learn more ↗
02

Concrete repair

Removal of damaged concrete, treatment of corroded rebar and rebuilding of the surfaces.

Learn more ↗
03

Bridge maintenance

Diagnosis, repair and restoration of bridges, viaducts and culverts.

Learn more ↗

OUTSIDE TUNISIA

How does a project outside Tunisia work?

  1. Your request

    Photos of the defects, drawings, inspection report, location: send us what you have, by email or WhatsApp.

  2. Review and site visit

    We review the file, then visit the structure to confirm the diagnosis and the method.

  3. Proposal

    Method, resources, schedule and price, prepared according to the client’s specifications.

  4. Works

    Our specialist teams and equipment on site, on our own or with a local contractor depending on the country, through to acceptance of the works.

IN AFRICA

Where this problem arises in Africa

Wadis in the Maghreb, the great rivers of West and Central Africa, the rivers of East and Southern Africa: wherever floods are strong, bridge foundations must be monitored and, if needed, strengthened.

OUR REFERENCES

Projects completed in Tunisia.

The Khmeyssia wadi bridge (Zaghouan): scoured foundations, jacketed footings, rebuilt embankments.

All our projects ↗

FAQ

Floods and scour: your questions.

What is scour?

It is the erosion of the ground around a bridge’s foundations by the current, especially during floods. The foundations can end up exposed.

Have you already repaired a scoured bridge?

Yes. On the Khmeyssia wadi bridge (Zaghouan), we strengthened the scoured foundations, jacketed the footings and rebuilt the approach embankments.

What should be done after a flood?

If the structure looks damaged, follow the authorities’ instructions, then have the bridge inspected by a professional; reopening it to traffic is for the authorities to decide.

What should we send you?

Photos of the defects, the location and, if possible, the drawings or the latest inspection report, by WhatsApp or email.

Do you work with a local contractor?

Depending on the country and the project, we work on our own or with a local contractor, through to acceptance of the works.

A PROJECT IN AFRICA?

Let’s talk about your project.

Send us your photos and the location on WhatsApp, or email us, and we will get back to you.

mohamed.biri@bbtp.com.tn